New energy secretary inherits five-year fight over Portsmouth Aquind plans
Portsmouth campaigners approach new energy secretary as opposition to Aquind continues
The campaigners who first challenged Aquind’s plans more than five years ago are still waiting for answers, as a sixth energy secretary inherits the dispute.
Miatta Fahnbulleh was appointed Secretary of State for Energy Security and Net Zero in July 2026, replacing Ed Miliband.
She is the latest minister to inherit responsibility for the proposed electricity link between Portsmouth and Normandy, which has been the subject of years of political decisions, legal challenges and local opposition.


A spokesperson for the Let’s Stop Aquind (LSA) campaign, has sent a letter to Ms Fahnbulleh introducing the group and setting out its objections to the project.
The campaign began after allotment holders and residents discovered plans to bring high-voltage electricity cables ashore at Eastney before taking them through Portsmouth and neighbouring areas to a new substation at Lovedean.
The proposed 2,000-megawatt interconnector would run beneath the English Channel from Normandy in France, with the UK cable coming ashore at Eastney.
From there, the route would pass through the eastern side of Portsmouth, including along Eastern Road, before continuing through Drayton, Purbrook and Waterlooville up to Lovedean.
Aquind says the £1.3bn project could provide enough electricity to meet up to five per cent of Great Britain’s annual energy use.
However, opponents argue the construction work would cause significant disruption to residents, businesses and the environment.
In it’s letter to Ms Fahnbulleh, LSA said the cable’s proposed route “through the most densely populated city second only to London” would cause “untold disruption and damage to the environment, to residents and businesses while adding to existing congestion and pollution along the route.”
The campaign has also raised concerns about the project’s ownership and national security, while Portsmouth City Council has opposed the proposed route.
How the project has reached this point
The Government’s involvement in the project dates back to 2018, when Aquind asked ministers to classify it as a Nationally Significant Infrastructure Project.
The designation meant the application would be decided by the Secretary of State through the national planning process.
Aquind formally submitted its application for a Development Consent Order in November 2019. The Planning Inspectorate accepted it for examination the following month.
The examination concluded in March 2021, with the examining panel later recommending that the project should receive development consent.
However, in January 2022, then Business Secretary Kwasi Kwarteng refused the application.
Aquind subsequently challenged the decision through a judicial review.
In January 2023, the High Court quashed the Government’s refusal, meaning the application had to be reconsidered by a Secretary of State.
The ruling did not grant Aquind permission to build the project. Instead, it meant the Government had to make a fresh decision.
Responsibility for that decision passed to the Department for Energy Security and Net Zero, which was created in February 2023.
The project then faced further delays after the Ministry of Defence raised serious national security concerns in 2024.
The MoD submitted objections to the Planning Inspectorate, saying further work was needed to address its concerns.
There was also a setback for the company in November 2024, when energy regulator Ofgem rejected its application to join a funding scheme designed to support new electricity interconnectors.
More recently, the project has encountered difficulties in France.
A refusal to grant a maritime concession was challenged by Aquind, with the matter taken to the French Administrative Court. A legal process which could take years has left the French side of the project facing further uncertainty.
A long-running campaign
Let’s Stop Aquind says its campaign has brought together residents, politicians and groups on both sides of the Channel.
It states that the campaign “grew rapidly” and it “soon united people of all political persuasions, local and national politicians, and residents of all nationalities, religious beliefs, and social standings, committed to defending our city and its environs against this destructive and unnecessary proposal.
“Our Facebook group has over 4000 members and is still growing. Large protests and rallies have been held, petitions presented to Parliament, one of which was presented in person to the Speaker by our own Stephen Morgan MP.”
In their email to Ms Fahnbulleh, LSA said it thought the MoD’s intervention would stop the project “once and for all” and that a decision from the government is “long overdue”.