Hilsea Lido, located in London Road, originally opened its doors to the people of Portsmouth back in 1935 by Portsmouth City Council. The facility was extremely popular but the over the years, the pool’s condition significantly deteriorated making it unsafe to use.
As a result, Portsmouth City Council launched a multi-million pound project to restore the pool to its former glory.
Once complete, the pool, which has been funded by the government’s Levelling Up Fund, will welcome a range of new facilities. These will include new changing rooms, new benches and tables, artwork, a fountain and, most importantly, a fully functioning outdoor swimming pool.
Work started in the summer of 2024 and the council has been working alongside consultancy company Mace, and contractors, Beard, to ensure progress is being made.
The fully renovated lido is expected to official open this summer in time for its 90th anniversary.
People have been able to keep up to date with the progress at the outdoor pool through key updates shared by the council.
So far, steel reinforcing for the balance tank from the deepest part of the pool has been installed. The first sections of the pool wall have also been formed and the shuttering has been removed.
A balance tank, which has been installed at the pool, is a crucial part of the system as it is a reservoir that helps maintain a consistent water level.
In addition to this, steel reinforcing is now in place along the restored 'lagoons' in the north side of the pool. All of the concrete is finished and the contractors have started preparing the ground for beach huts.
Now the initial phase of the project has been completed, the contractors will move onto the building phase. This work will include new pipework which will be installed in deep trenches, the pool and the surrounding area will be restored, and new modular changing units will be installed.

25. Hilsea Lido 2026
Hilsea Lido is now full of water. The pool currently doesn't have any chemicals in it and the filters haven't been switched on yet. It is being tested, so the contractors will leave the pool at this level for a week, with a surveyor regularly measuring the water levels. After this the pool will be filled completely, and pool experts Barr and Wray will come and turn the filters on. | PCC

26. Hilsea Lido
Hilsea Lido has announced its opening date. Pictured: Councillor Lee Hunt, Cabinet Member for Community Safety, Leisure & Sport, Judit Kollat, Hilsea Lido General Manager, Duncan Anderson, CEO South Downs Leisure and Councillor Steve Pitt, Leader of Portsmouth City Council. | Sea Lanes

27. Hilsea Lido
The protective tent at Hilsea Lido has been fully dismantled after being in place for almost a year. Picture: Marcin Jedrysiak | Marcin Jedrysiak

28. Hilsea Lido
The protective tent at Hilsea Lido has been fully dismantled after being in place for almost a year. Picture: Marcin Jedrysiak | Marcin Jedrysiak