The £7.75m scheme, which is being paid for by the Levelling Up Fund and carried out by Beard, will see new changing rooms, benches, tables, fountain and a fully functioning pool.
The Portsmouth City Council, who is overseeing the renovation has provided a new update confirming that tiling has officially started at the site.
A spokesperson said that horizontal tiles are going along the edge of the pool, along with the finger rests, and once this is done horizontal tiles will be placed on the other side of the drainage gulley and a final row of vertical tiles will go along the top of the pool.
Large sections of the pool floor have now also been rendered to create a smooth surface ready for the final epoxy coating and the haul road outside has been removed.
The Portsmouth City Council has previously said the anticipated opening date will be early autumn.

. Hilsea Lido - June 2025
The team have started putting horizontal tiles around the edge of the pool, along with the black finger rests. Next, they will put the horizontal tiles on the other side of the drainage gulley. | PCC

5. Hilsea Lido - June 2025
Large sections of the pool floor are now being rendered to create a smooth surface for the final epoxy coating. A two-metre gap is being left around the edges, so tiling can carry on without interruption. That area will be rendered later. | PCC

6. Hilsea Lido - June 2025
Concrete bases have been installed at the shower units at the western end of the site. | PCC