The outdoor pool originally opened its doors back in 1935 by Portsmouth City Council but its condition significantly deteriorated over the years, making it unsafe to use.
Following multiple consultations, a multi-million pound project was launched last year to completely restore the pool to its former glory. The pool, which will open in the summer, will feature new changing rooms, new benches and tables, artwork, a fountain and, most importantly, a fully functioning outdoor swimming pool.
In the most recent updates, the pool has been completely concreted and the contractors are currently pumping water out of the pool that collected in there over Christmas.
Bright shower unit cabins have now been installed at the lido. They need to be plumbed in and have gas and electrical connections completed.
The plant room floor has been concreted, and work will start to reinforce the walls. Three filtration tanks will be installed in the plant room in due course.

149. Hilsea Lido: New Drainage - August 2024
New drainage around the pool has now been laid, ready for the resurfacing of the pool area later this year. | Portsmouth City Council

150. Hilsea Lido: New Ledge - August 2024
A brand new ledge will mean that visitors will be able to sit on the edge of the pool and safely dangle your feet in, or perch on the ledge itself. | Portsmouth City Council

151. Hilsea Lido - July 2024
The Portsmouth City Council has issued an update on the Hilsea Lido which is undergoing a multi-million pound regeneration. Photo: Portsmouth City Council

152. Hilsea Lido - July 2024
The Portsmouth City Council has issued an update on the Hilsea Lido which is undergoing a multi-million pound regeneration. Photo: Portsmouth City Council