Over the years, the pool’s condition significantly deteriorated making it unsafe to use. As a result, a multi-million pound project has been launched to restore the pool to its former glory by completely renovating it.
Work started at the beginning of the summer of 2024 with the council working alongside consultancy company Mace, and contractors, Beard, to ensure progress is being made.
The outdoor pool will welcome new changing rooms, new benches and tables, artwork, a fountain and, most importantly, a fully functioning outdoor swimming pool.
Portsmouth City Council started posting updates surrounding the project in June of last year - and the work that has already been completed is incredible.
Steel reinforcing for the balance tank from the deepest part of the pool has been installed. The first sections of the pool wall have also been formed and the shuttering has been removed.
A balance tank, which has been installed at the pool, is a crucial part of the system as it is a reservoir that helps maintain a consistent water level.
In addition to this, steel reinforcing is now in place along the restored 'lagoons' in the north side of the pool. All of the concrete is finished and the contractors have started preparing the ground for beach huts.

145. Hilsea Lido - September 2024
Portsmouth City Council has issued an update on the progress of Hilsea Lido. Pictured: The base of the pool full of steel bars, ready for the final concrete pour. | Portsmouth City Council

146. Hilsea Lido - September 2024
Portsmouth City Council has issued an update on the progress of Hilsea Lido. Pictured: The backwash tank fitted into place – this will be covered but will be accessible by a manhole cover. | Portsmouth City Council

147. Hilsea Lido - September 2024
Portsmouth City Council has issued an update on the progress of Hilsea Lido. Pictured: The 10.5m long backwash tank being lifted into place. | Portsmouth City Council

148. Hilsea Lido: Concrete Pour - August 2024
The team have continued to pour concrete into the bottom of the pool, with another 750mm to go on the level shown above. The 'pressure release wells' that the team saw in last fortnight's bulletin have mainly been covered up. Once finished, the pool will be 2.6m deep at the lowest point. Once this is complete, the first of the stainless steel dowels will go in to reinforce the pool, before it is re-lined. | Portsmouth City Council